Americans voted on 41 data center ballot measures in the 2026 midterm elections. In all but one of these measures, Americans voted to restrict data center development. While Congress has a role to play, the fine print will be hammered out in state legislatures. The states will decide whether “making data centers pay their own way” amounts to punitive restrictions that drive out investment, or whether it means sensible cost-causation principles that protect ratepayers while encouraging innovation.
The U.S. Senate is considering the Bipartisan American Affordability and Jobs Act (BAAJA), which among other permitting and transmission reforms, would establish “a formal national policy requiring data centers and computational loads to bear their full incremental grid infrastructure and embedded transmission service costs.” The initial bill only had this provision apply to data centers drawing 20 megawatts (MW) of power or more, but the substitute amendment dropped the threshold, so it would apply to all data centers. A final vote is expected the week of November 16th, but some Democrats seem likely to try to stall, or substantially amend, the bipartisan legislation.
Even if BAAJA passes, the decisions that most directly affect data centers are made in state capitals and in regulatory bodies. Federal regulators oversee interstate transmission and wholesale power markets, but under the Federal Power Act, states have extensive power to regulate the electricity generated and sold within their borders, including over generation facilities, local distribution, and retail sales.
For instance, in Texas, almost everything is left to the state to decide, and the incoming governor has promised a moratorium before she has even taken office. Governor-elect Gina Hinojosa (D) called for “an immediate moratorium on data centers” at least until the legislature implements its own standards, continuing Governor Greg Abbott’s permit pause and audit. Ms. Hinojosa has also promised to “declare a high-cost emergency” and “freeze electricity rates.” Better options are already before Texas lawmakers in interim committees, including bring-your-own-power, which would prevent cost shifting to Texas families and would rely on voluntary contracts.
Moratoriums, by necessity, assume that data centers are driving up electricity rates. The research does not support that. A September 2026 study by researchers at the University of Pennsylvania and Harvard Business School found that additional data centers built in the U.S. between 2020 and 2025 explained only 4% of the observed increase in residential prices since 2020. The researchers’ findings also suggest that hyperscale data center additions “by Big Tech firms” actually “result in no discernible price increases,” but that smaller, co-location data centers do.
The authors conclude that “the prevailing discourse about data centers affecting electricity affordability is overstated, and that the average residential price effect is small.”
The 2027 legislative sessions will determine whether states follow the lead of New York with moratoriums, or let data centers pay their own way and bring their own power.